Footpath Upgrades Within Buloke

Upgrading Footpaths Within Buloke - May 2024

Publish Date 29 May 2024

Buloke footpaths are getting a make-over!

Developments are underway in Buloke as our footpaths undergo a much-awaited transformation!

MF & JL Willmores Pty Ltd has been engaged to complete the works and affected property owners will be advised by letter of the works timetable and any issues around access to properties.

With successful completions in Berriwillock, Birchip, Charlton, Donald and Watchem, residents can anticipate similar enhancements when works are completed at Nullawil, Sea Lake and Wycheproof.

For any inquiries, the Council is readily available at 1300 520 520.

 
Wycheproof

Works in the Township of Wycheproof are to commence in May 2024 and is estimated to be completed June 2024.

Sl no

Town Name

Street Name

1

Wycheproof

High Street

2

Wycheproof

O’Connor Street

3

Wycheproof

Jolly Street

4

Wycheproof

Webster Steet

5

Wycheproof

Chapel Street

6

Wycheproof

Dempsey Street

8

Wycheproof

Mount Street

9

Wycheproof

Prospect Street

10

Wycheproof

Hillview Street

11

Wycheproof

Grandview Street

Sea Lake

Works in the Township of Sea Lake will commence in May 2024 and is estimated to be completed start July 2024.

footpaths 1 image

Sl no

Town Name

Street Name

1

Sea Lake

Sutcliff Street

2

Sea Lake

Best Street

3

Sea Lake

Hannon Street

4

Sea Lake

Howard Street

6

Sea Lake

Cox Street

7

Sea Lake

Mudge Street

8

Sea Lake

Gregson Street

9

Sea Lake

Wilkinson street


birchip footpath

 

 

 

 