Publish Date 23 October 2023
Buloke footpaths are getting a make-over!
MF & JL Willmores Pty Ltd has been engaged to complete the works and affected property owners will be advised by letter of the works timetable and any issues around access to properties.
Works have been undertaken in Birchip and Watchem (Aug- Sept) and Charlton (Sept-Oct).
Works have now commenced in Donald (Oct-Nov) and are scheduled to continue in Wycheproof and Nullawil (Nov -Dec), Sea Lake and Berriwillock (Jan-Mar 24).
If you have any questions, please contact Council on 1300 520 520.
Capital Works Timetable as at 23 October 2023
Donald
Works in the Township of Donald has commenced in October 2023 and is estimated to be completed by mid November 2023.
Sl no
Town Name
Street Name
1
Waddell street
2
Camp Street
3
Houston Street
4
Wood Street
5
Campbell Street
6
Blair Street
8
Hammill Street
9
McCollough Street
10
Mill Street
11
Park Street
12
Meyer Street
13
Waddell Street
14
South Street
Wycheproof and Nullawil
Works in the Township of Wycheproof and Nullawil commence mid November 2024 and is estimated to be completed mid December 2023.
Wycheproof
High Street
O’Connor Street
Jolly Street
Webster Steet
Chapel Street
Dempsey Street
Mount Street
Nullawil
Baxter Street
Prospect Street
Hillview Street
Grandview Street
Sea Lake and Berriwillock
Works in the Township of Sea Lake and Berriwillock will commence late January 2023 and is estimated to be completed start March 2024.
Sea Lake
Sutcliff Street
Best Street
Hannon Street
Howard Street
Berriwillock
Taverner Street and Morris Street Intersection
Cox Street
Mudge Street
Gregson Street
Wilkinson street